Quiz Summary
0 of 80 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 80 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
-
You have not reached the necessary score to guarantee you pass the exam !!!
Don’t hesitate to consolidate your preparation with our other quizzes : https://crossprep.org/categorie-produit/exam-prep
The key of success is your preparation
-
Congratulation you reached the targeted score !!!
Don’t hesitate to consolidate your preparation with our other quizzes : https://crossprep.org/categorie-produit/exam-prep
The key of success is your preparation
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 80
1. Question
Which of the following is NOT an advantage of using Scrum to deliver projects?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 2 of 80
2. Question
Which of the following is a valid service from the Scrum Master to the Product Owner?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 3 of 80
3. Question
Which of the following statements about the Scrum framework is TRUE?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 4 of 80
4. Question
Which of the following statements best describes a Scrum Team?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 5 of 80
5. Question
The Agile Manifesto states that we value individuals and interactions _____ processes and tools.(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 6 of 80
6. Question
What is the purpose of the Sprint Review?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 7 of 80
7. Question
Which concept is the basis of the business justification aspect in Scrum?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 8 of 80
8. Question
Every Sprint cycle begins with a _____________ meeting.(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 9 of 80
9. Question
How long can a Sprint be if a team takes four-hours in Sprint Planning?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 10 of 80
10. Question
When does the Sprint end?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 11 of 80
11. Question
What is management’s role in Scrum?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 12 of 80
12. Question
What would likely happen if management only changed the organization’s current terminology to fit Scrum without the proper understanding and support of Scrum as defined in the Scrum Guide?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 13 of 80
13. Question
Flexibility in Scrum is NOT achieved through which of the following?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 14 of 80
14. Question
Which statement best describes Scrum?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 15 of 80
15. Question
True or False: In order to start the first Sprint, Scrum only requires a Product Owner with enough ideas, Developers to execute on those ideas, and a Scrum Master to guide the process.Choose only ONE best answer.
CorrectIncorrect -
Question 16 of 80
16. Question
Scrum is based on which of the following?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 17 of 80
17. Question
True or False: Stakeholders are only allowed to meet with the Scrum Team at Sprint Review.Choose only ONE best answer.
CorrectIncorrect -
Question 18 of 80
18. Question
Which of the following items should NOT be raised during a retrospective meeting?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 19 of 80
19. Question
Which Scrum Value impacts trust?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 20 of 80
20. Question
Doing your best and helping other Scrum Team members demonstrates which of the following?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 21 of 80
21. Question
Peter, a Project Manager, has raised concerns about your Scrum Team’s productivity and progress towards the objectives. Which is the best way to respond to Peter’s concerns?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 22 of 80
22. Question
The three pillars of empirical process control consist of:(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 23 of 80
23. Question
If burn-down charts are used to visualize progress, what does a trendline projection through a release burn-down chart indicate?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 24 of 80
24. Question
What is a good way for a Scrum Team to ensure that security concerns are addressed and transparent?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 25 of 80
25. Question
True or False: Technical Debt can lead to false assumptions about the current state of the system and the Increment reviewed at the end of the Sprint.Choose only ONE best answer.
CorrectIncorrect -
Question 26 of 80
26. Question
True or False: When technical debt occurs, the system will become more unstable as development progresses and code is added resulting in future work being slowed down.Choose only ONE best answer.
CorrectIncorrect -
Question 27 of 80
27. Question
Who can change the Sprint Backlog in the middle of the Sprint?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 28 of 80
28. Question
At the eighth Sprint Review, the stakeholders are upset that the product being built is not what they expected and will incur additional costs that was not planned for. What may have led to this?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 29 of 80
29. Question
Select the correct Scrum Team members defined in Scrum.(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 30 of 80
30. Question
True or False: Scrum has a role called Project Manager.Choose only ONE best answer.
CorrectIncorrect -
Question 31 of 80
31. Question
A Scrum Team has been working on the same product for 12 Sprints. What would likely be the immediate impact on the original Scrum Team if two new Scrum Teams are to be added the same product?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 32 of 80
32. Question
What would be the main benefits of self-managing?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 33 of 80
33. Question
True or False: A Scrum Team must have a Product Owner and Scrum Master.Choose only ONE best answer.
CorrectIncorrect -
Question 34 of 80
34. Question
In what ways does the Scrum Master keep the Developers working at their highest level of productivity?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 35 of 80
35. Question
Which of the following statements are true about the Scrum Master role?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 36 of 80
36. Question
Flexibility on Scrum projects is achieved through which of the following?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 37 of 80
37. Question
A Scrum Team, with remote Developers, typically spends extra time before the Daily Scrum to setup the meeting rooms and conference calling equipment and tools in order to have their Daily Scrum. How should the Scrum Master handle this situation?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 38 of 80
38. Question
Which statement is correct when the Developers are working in the middle of the Sprint?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 39 of 80
39. Question
A Developer has notified the Scrum Master of a potential data security risk. What action should the Scrum Master take?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 40 of 80
40. Question
A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which would be the LEAST helpful technique in this situation?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 41 of 80
41. Question
Your organization has formed a new Scrum Team and has assigned you as the Scrum Master. In what ways would help the team start?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 42 of 80
42. Question
What guideline should the Scrum Master provide if the Product Owner asks how estimations should be made in Scrum?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 43 of 80
43. Question
The Developers discover that they don’t have the tools and infrastructure to make each selected Product Backlog item done. What is the most appropriate action for the Scrum Master to take?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 44 of 80
44. Question
The Developers have suggested to move the Daily Scrum to every other day instead of every day. What is the most appropriate action for the Scrum Master to take?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 45 of 80
45. Question
Which of the following events is conducted at the end of a Sprint to analyze process improvement opportunities for the future Sprints?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 46 of 80
46. Question
What action can the Scrum Master take to ensure communication between the Developers and Product Owner is effective?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 47 of 80
47. Question
How should a Scrum Master coordinate the work when more than one Scrum Team is working on one product?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 48 of 80
48. Question
What would be typical Scrum Master activities during the Sprint?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 49 of 80
49. Question
True or False: The Scrum Master is responsible for the process in which Scrum is adopted and enacted.Choose only ONE best answer.
CorrectIncorrect -
Question 50 of 80
50. Question
As a Scrum Master, you observe that the Product Owner is not effectively collaborating with the Developers. What actions would you take?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 51 of 80
51. Question
True or False: A Scrum Master teaches those who are interested in the Developers’ progress that progress in Scrum comes from inspecting an Increment at the Sprint Review.Choose only ONE best answer.
CorrectIncorrect -
Question 52 of 80
52. Question
What is sustainable pace?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 53 of 80
53. Question
Which of the following statements best describes collaboration?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 54 of 80
54. Question
What is the most appropriate action for the Scrum Master to take if the Product Owner is having difficulties managing the Product Backlog?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 55 of 80
55. Question
What is a Product Owner responsibility that he/she might delegate?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 56 of 80
56. Question
What action should a Scrum Master take if the Developers have decided that Retrospectives are no longer necessary?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 57 of 80
57. Question
Which stakeholder is the most important for the Product Owner to satisfy?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 58 of 80
58. Question
As a Scrum Master, what would you strive for if five new Scrum Teams were to work on one product?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 59 of 80
59. Question
Customer satisfaction should be measured:(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 60 of 80
60. Question
Several Sprints into a project, a client is complaining to the Product Owner about the poor performance of the product. As a Scrum Master, how can you help the Product Owner?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 61 of 80
61. Question
Why is it important that there is only one Product Owner per product?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 62 of 80
62. Question
True or False: The Product Owner’s primary concern is the flow of value reflected in the ordering of the Product Backlog.Choose only ONE best answer.
CorrectIncorrect -
Question 63 of 80
63. Question
Which of these tools is mandatory for the Product Owner to use?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 64 of 80
64. Question
Why does the agile manifesto de-emphasize extensive documentation early in the project?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 65 of 80
65. Question
During Sprint Planning, the Developers were not able to confidently forecast a Sprint Backlog but the Scrum Team was able to create a Sprint Goal for upcoming Sprint. Which action would a Scrum Master support?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 66 of 80
66. Question
A new Product Owner is hired to work on an existing product that has ongoing for five Sprints. He/she is unsure about all of the responsibilities of a Product Owner. Which of these Product Owner activities would be most helpful?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 67 of 80
67. Question
How should a Scrum Master divide a group of 100 Developers into multiple Scrum Teams?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 68 of 80
68. Question
Which is the best description of a Product Owner?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 69 of 80
69. Question
You are the Scrum Master for four Scrum Teams working on one product. Several of the developers notify you that their teams will need full-time help of an external technical specialist in the upcoming two Sprints. What key concerns should the Scrum Master take into account?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 70 of 80
70. Question
Who is responsible for ensuring the Product Backlog items are understood to the level needed.(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 71 of 80
71. Question
Which of the following actions are appropriate for a Scrum Master at the Daily Scrum?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 72 of 80
72. Question
What activities would a Product Owner do during an active Sprint?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 73 of 80
73. Question
Who on a Scrum Team would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 74 of 80
74. Question
Peter is a new Product Owner on a newly formed Scrum Team. Peter has projected a product completion date based on an estimated velocity of 21 completed points per Sprint. After the first 3 Sprints, the team has determined that their maximum velocity is 15 points and they are unable to create shippable increments at the end of each Sprint. What is the best way to proceed?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 75 of 80
75. Question
Which of the following are true about the Product Owner role?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 76 of 80
76. Question
Who manages the progress of work during a Sprint?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 77 of 80
77. Question
True or False: A PO (Product Owner) is essentially the same thing as a traditional PM (Project Manager).Choose only ONE best answer.
CorrectIncorrect -
Question 78 of 80
78. Question
What should the Developers do if they are approached by someone outside the team and asked to add a very important item to a Sprint that is in progress?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 79 of 80
79. Question
Which Scrum Team member is responsible for engaging with stakeholders?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect -
Question 80 of 80
80. Question
How much work must the Developers do to a Product Backlog item that had been selected for a Sprint?(choose the best answer)Choose only ONE best answer.
CorrectIncorrect