CAPM Mock Exam LITE 6
May 9, 2023
Quiz Summary
0 of 51 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 51 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 51
1. Question
1. Which of the following graphical techniques visually depict the product scope by showing a business system and how other systems interact with it?
CorrectIncorrect -
Question 2 of 51
2. Question
2. You have recently become the project manager for a construction project. You are a new hire in your company and are unaware of the organizational project management standards. Which of the following can help you get a head start on your project?
CorrectIncorrect -
Question 3 of 51
3. Question
3. Which of the following statements is not accurate about the initial phase of a project?
CorrectIncorrect -
Question 4 of 51
4. Question
4. Chris is managing a construction project. The project team is currently developing the “as built” construction drawings to be supplied to the client as required by the contract. Which of the following phases is Chris’ project most likely in?
CorrectIncorrect -
Question 5 of 51
5. Question
5. In predictive projects, the scope baseline for the project is used to analyze a project’s scope performance. On the other hand, projects with adaptive lifecycles use:
CorrectIncorrect -
Question 6 of 51
6. Question
6. Which process group corresponds to the “do” part of the plan-do-check-act cycle?
CorrectIncorrect -
Question 7 of 51
7. Question
7. You have recently taken over a project as the project manager. The project is midway through execution, and most of the project work has been subcontracted. You have just found out that one of the subcontractors, who was responsible for all demolitions, has been paid 50 percent of the subcontracted value, but he has delivered only 25 percent of the required works. Upon investigation, you learned that all the payments are in line with the signed contract between the two parties and the subcontractor’s work is compliant with the contract specifications. You are annoyed because this does not give you enough control over the subcontracted works. Which of the following is not an appropriate thing to do at this stage?
CorrectIncorrect -
Question 8 of 51
8. Question
8. Your company is considering buying a building worth $1 million. If the company buys this building and rents it out for the next five years, it will get $100,000 per year as rent (receivable by the end of each year). At the end of the fifth year, the company will resell the building at $1.1 million. What is the NPV of this investment at 10 percent per annum discount rate?
CorrectIncorrect -
Question 9 of 51
9. Question
9. Andrew is a project management guru hired by a retail giant in your country. Andrew finds out there is a wide array of projects that need to be managed from a central PMO; from a number of small projects to large initiatives requiring long-term roadmaps to manage the development of these programs. What project management approach should be recommended for such projects?
CorrectIncorrect -
Question 10 of 51
10. Question
10. Organizational process assets are fundamental inputs to most of the project management processes. However, only some of the process assets are relevant to any given process. Which of the following organizational process assets is the least important consideration during the Manage Stakeholder Engagement process?
CorrectIncorrect -
Question 11 of 51
11. Question
11. The paint on the exotic cars that are manufactured in your plant is bubbling about a year after application. What would be the best tool for your team to use to find potential causes of the peeling paint?
CorrectIncorrect -
Question 12 of 51
12. Question
12. Early in the project, you are meeting with your team and would like to address all the strengths, weaknesses, opportunities, and threats the project is facing. What tool should be used?
CorrectIncorrect -
Question 13 of 51
13. Question
13. You recently took over a project as the project manager. This is your first project management assignment. The project sponsor is very supportive and is helping you out in successfully managing the project. Recently, some bad quality deliverables were received on the project, and the project sponsor suggested that you to periodically review the vendor’s progress to deliver project scope and quality, within cost and on schedule, as compared to the contract. Which of the following statements is true in this context?
CorrectIncorrect -
Question 14 of 51
14. Question
14. You are in charge of constructing the Ferris wheel in each town a carnival visits. However, this is something you have never done before, and you are getting different opinions from others on how long it takes. Joe is new and has given you what you believe to be an optimistic estimate of three hours; Bill says it will take 10 hours, which seems too long to you and quite pessimistic. Last, Margie, who is the most experienced at this task, is telling you it will take eight hours. You are not sure whom to believe, so you decide to do three-point estimation (based on beta distribution). Based on this, how many hours will it take you to assemble the Ferris wheel?
CorrectIncorrect -
Question 15 of 51
15. Question
15. PMBOK® Guide offers a number of tools and techniques for all the project management processes. These tools and techniques must be carefully applied in order to meet the objectives of any process. Which of the following is not a tool or technique of the Plan Stakeholder Engagement process?
CorrectIncorrect -
Question 16 of 51
16. Question
16. Business value is also defined as the aggregate of all tangible and intangible elements of the business. Which of the following is NOT an example of a tangible business element?
CorrectIncorrect -
Question 17 of 51
17. Question
17. You have just returned from the weekly change control board meeting at which you presented the requested changes to the employee move project. You had five change requests approved and one request rejected. These are outputs of what process?
CorrectIncorrect -
Question 18 of 51
18. Question
18. There are two activities on your schedule: 1) Install server in lab, and 2) Move server into the data center. However, the second task cannot start until the server has run in the lab for five days without failure. This is an example of what?
CorrectIncorrect -
Question 19 of 51
19. Question
19. Your construction project is in execution, and you require a major change to one of your supplier agreements. Can you directly make this change with mutual consent of the supplier during the Control Procurements process, or do you have to visit the Perform Integrated Change Control process, as well?
CorrectIncorrect -
Question 20 of 51
20. Question
20. A change log is an important input to the Manage Stakeholder Engagement process. Which process provides this input?
CorrectIncorrect -
Question 21 of 51
21. Question
21. In your weekly status reports, you report the earned value for the project. This information is essential for you and the stakeholders to gauge the progress of the project. What process group is the cost and schedule control part of?
CorrectIncorrect -
Question 22 of 51
22. Question
22. You are having your project team members record the time they spend on different activities during the day, such as programming, electrical, HVAC, etc. This is an example of a tool and technique in what process?
CorrectIncorrect -
Question 23 of 51
23. Question
23. You are working with your team and are looking at the cost risks in the project. You and your team are currently creating a tornado diagram for the project risks. You do this as a part of which of the following processes?
CorrectIncorrect -
Question 24 of 51
24. Question
24. Stakeholder notifications must be archived for future reference. Whenever the Manage Communications process produces a stakeholder notification, the notification must be:
CorrectIncorrect -
Question 25 of 51
25. Question
25. Communication noise refers to influences on effective communication that influence the interpretation of conversations. Noise affects which components of communication?
CorrectIncorrect -
Question 26 of 51
26. Question
26. You are in the execution stage of your project, and you are informed that “corporate” will send in a team of consultants to review whether your project activities comply with your company’s and PMI’s policies, standards, and procedures. This is an example of:
CorrectIncorrect -
Question 27 of 51
27. Question
27. You are in the initiation phase of your project, and you believe the project can be completed for $100,000. However, you are an experienced project manager and know that many things can happen between the initiation phase and the closure of the project. In the project charter, you have provided an estimate of $75,000 to $175,000. This is an example of:
CorrectIncorrect -
Question 28 of 51
28. Question
28. PMBOK® Guide recognizes five process groups typical of nearly all projects. Which of the following is not one of them?
CorrectIncorrect -
Question 29 of 51
29. Question
29. A technique that calculates multiple project durations with different sets of activity assumptions and variables is:
CorrectIncorrect -
Question 30 of 51
30. Question
30. Project stakeholder management is an integral part of project management. The effectiveness of stakeholder analysis carried out early in a project can decide its fate. Which of the following is the least important consideration during stakeholder analysis, especially when analyzing stakeholders who are also decision-makers?
CorrectIncorrect -
Question 31 of 51
31. Question
31. A process that states how formal validation and acceptance of the completed project deliverables will be achieved is documented in the:
CorrectIncorrect -
Question 32 of 51
32. Question
32. The WBS is a deliverable-oriented hierarchical decomposition of the work the project team must execute to accomplish the project objectives. This is created as part of:
CorrectIncorrect -
Question 33 of 51
33. Question
33. Which of the following Manage Quality techniques examines problems, constraints, and non-value-added activities that occur during project work?
CorrectIncorrect -
Question 34 of 51
34. Question
34. On any project, the configuration control should be focused on the specification of:
CorrectIncorrect -
Question 35 of 51
35. Question
35. Complex projects usually demand preparation and distribution of periodic project performance reports. The contents of performance reports are usually determined early and documented in the project communications management plan. Which of the following is least likely to be a section on a work performance report?
CorrectIncorrect -
Question 36 of 51
36. Question
36. Andy’s project stakeholders are not happy as the project is lagging behind schedule. During the executive committee meeting, Andy requests all stakeholders to keep their calm as most of the project deliverables have been completed and only quality inspections of these deliverables is pending. He assures the stakeholders that he is planning to crash the project to meet the completion deadline. What should be the stakeholders’ biggest concern now?
CorrectIncorrect -
Question 37 of 51
37. Question
37. A change request that is issued to bring the performance of the project back in line with the project management plan is related to:
CorrectIncorrect -
Question 38 of 51
38. Question
38. Which of the following tools give a visual representation of an organization’s data, described in business language that is independent of any specific technology?
CorrectIncorrect -
Question 39 of 51
39. Question
39. You are running one week behind on a project due to a late delivery by a vendor. You are forced to compress your project schedule due to a government-mandated end date that constrains your project. After meeting with your team, the decision is to work several tasks in parallel that were scheduled to be run consecutively. This is an example of:
CorrectIncorrect -
Question 40 of 51
40. Question
40. While developing your project schedule, you have asked everyone to provide a list of planned vacations over the next three months, and you have applied this information to the tasks that each person is responsible for. What also needs updating?
CorrectIncorrect -
Question 41 of 51
41. Question
41. A project has gone out of control, and the project manager is trying to bring it back under control. There have been a number of changes to the project scope. Some of these changes resulted in further changes, causing project cost to spiral upward and causing the project to go out of schedule. This is known as:
CorrectIncorrect -
Question 42 of 51
42. Question
42. Mary is managing an organizational transformation project. The nature of the project would require responding to high levels of change and would also require continuous stakeholder engagement. Which of the project lifecycles should be chosen for this project?
CorrectIncorrect -
Question 43 of 51
43. Question
43. Crashing is an effective schedule compression technique at times when a project is struggling behind schedule. However, increasing the number of resources to twice the original number of the resources does not always cut the time by half. This is due to:
CorrectIncorrect -
Question 44 of 51
44. Question
44. Which of the following statements is incorrect?
CorrectIncorrect -
Question 45 of 51
45. Question
45. You are an experienced project manager and have managed several data center migration projects. You are currently conducting training on the databases, spreadsheets, and management plans you will use during the lifecycle of the project. This training is a tool and technique in what process?
CorrectIncorrect -
Question 46 of 51
46. Question
46. You are managing an oil-drilling project. With oil at $143 per barrel, this could be a highly lucrative project. However, there is a chance that the price of oil will drop below $105 per barrel, which would eliminate the profit in the project. This is an example of:
CorrectIncorrect -
Question 47 of 51
47. Question
47. During the weekly change control board meeting, you invited the facilities manager to speak about the change request to increase the BTUs of the air conditioning system in the new data center. This is an example of what type of tool and technique in the Perform Integrated Change Control process?
CorrectIncorrect -
Question 48 of 51
48. Question
48. You are managing a project that has a task to translate several pages of a document into Spanish. This is similar to a project done last year when a document was translated into German. You are not sure how long it will take to translate into Spanish, so you look at the project plan from the German translation and use that activity duration for your current project. What type of estimating is this an example of?
CorrectIncorrect -
Question 49 of 51
49. Question
49. To control the schedule, a project manager is reanalyzing the project to predict project duration. This is done by analyzing the sequence of activities with the least amount of flexibility. What technique is being used?
CorrectIncorrect -
Question 50 of 51
50. Question
50. A project manager creates a component-specific tool to verify that a set of required steps has been performed. This tool is called a:
CorrectIncorrect -
Question 51 of 51
51. Question
51. The complexity of the information flow in any project depends upon the complexity of the project itself. Information flows through various channels in complex projects. The project management team is responsible for gathering, compiling, analyzing, and reporting this information. Which of the following processes finally releases the project information to the project stakeholders?
CorrectIncorrect